Sanitary Sewer Rehab Phase 7

WHAT: Sanitary Sewer Rehab Phase 7

WHY: Repair of existing sanitary sewer (broken pipes, insufficient slope, etc.)

WHEN: Started November 10, we have asked contractor for a more detailed schedule of when they will be working in what areas.

WHO: Champion Cleaning Specialists, Inc.

HOW MUCH: Total of 7610 linear feet of cured in place pipe (sizes are 15”, 18”, 24”)

DURATION: 180 Days (Finished by May 2026)